3) list of ventilation equipment supplied by the customer;

4) characteristics of air ducts for ventilation systems and a list of installation drawings or sketches on them;

5) schedule of receipt of ventilation blanks (ducts and standard ventilation parts) to the facility;

6) the schedule of receipt of ventilation equipment, agreed with the customer;

7) calendar (network) schedule of work with deadlines for the delivery of the object;

8) statement of basic and auxiliary materials;

9) instructions on methods and methods of installation work and safety;

10) a statement of the necessary mechanisms, tools and means of small mechanization specifically for the object;

11) production calculations and summary statements of labor costs and wages;

12) the schedule of the need for workers.

In the calendar (network) schedule of work, the deadlines for preparing the object or individual premises for installation, the deadlines for the completion of construction work in ventilation chambers, the deadlines for the supply of electricity to ventilation equipment and hot water to heaters and, most importantly, the deadlines for the installation of ventilation systems should be determined. A schedule for the delivery of ventilation equipment to the facility must be agreed with the customer's organization in advance.

For objects with a small amount of ventilation work and capital repairs, abbreviated The project of work production is the basic guide for the organization and production of installation work at the facility. Project of work production helps to plan all the preparatory work, including the execution of orders for air ducts and applications for ventilation equipment and materials, to determine the storage locations of bulky ventilation parts. The project of work production contributes to the uninterrupted conduct of installation work, improving the quality of installation.

7.2. Acceptance of the object for installation work

Prior to the start of installation work on the object or on its part, a list of individual types of construction works, the performance of which is necessary for the subsequent installation of ventilation systems, and the timing of their execution must be agreed between the representatives of the installation organization and the general contractor.